Project Overview
Joe Wagner Group was engaged as Principal Contractor by Queensland Rail to deliver formation upgrades along 3.2km of the Blaxland rail corridor. The works were delivered under a 96-hour possession, with extensive preparation completed prior to the shutdown.
Project Scope
- Cut and strip rail from the existing line
- Remove and replace formation and ballast
- Remove and replace existing sleepers (QR scope)
- Deliver site preparation for delivery of sleepers and rail
- Manage rail shutdown and logistics under 24-hour schedule
- Flood with ballast and reinstate site conditions post-works
Project Outcomes / Highlights
- Maintained full program in severe weather and soft ground conditions using bog mats
- 24-hour operations with zero disruptions to adjoining services
- Delivered under budget and with no safety incidents
- Enabled long-term serviceability and reliability of the corridor
Client
Queensland Rail
Location
Blaxland, West Moreton Line, QLD
Value
$1.1M
Project Duration
96-hour rail shutdown