IPAC 2 – Kogan Creek Power Station
IPAC 2 – Kogan Creek Power Station
Project Overview
Joe Wagner Group was contracted by CS Energy to deliver the civil works for the second In-Pit Ash Cell (IPAC 2) at the Kogan Creek Power Station. The works were integral to long-term ash management and environmental compliance for the site.
Project Scope
- Dam wall construction with 4,000 m³ of select fill
- Subgrade prep and installation of 110,000 m² LLDPE liner
- Ground surface treatment using impact rollers
- 6,400 m³ of riprap for spillway protection
- Drainage works including 750mm crest drainage and culverts
- Pavement works and erosion control measures
Project Outcomes / Highlights
- Delivered despite major rainfall and site evacuation
- Maintained program using effective dewatering plans
- No LTIs; coordinated with Fab Tech for liner install
- Enhanced operational readiness for ash management
Client
CS Energy
Location
Brigalow, QLD
Value
$4.5M
Project Duration
6 months