Macintyre Wind Farm – Intersection Upgrades
Macintyre Wind Farm – Intersection Upgrades
Project Overview
To enable safe delivery of oversized turbine components, Joe Wagner Group completed road and intersection upgrades across a 12-site route from the Port of Brisbane to the Macintyre Wind Farm.
Project Scope
- Intersection and roundabout upgrades across key haul routes
- Road widening and pavement strengthening
- Bulk earthworks, subgrade prep, and asphalt surfacing
- Kerbs, drainage, signage, and lighting modifications
- Traffic management design and environmental controls
- Full reinstatement of disturbed areas
Project Outcomes / Highlights
- Delivered to a compressed 2-month schedule
- Collaborated with Qube, TMR, and local councils
- Enabled milestone turbine component deliveries
- Integral to Australia’s renewable energy infrastructure rollout
Client
Qube Bulk
Location
Brisbane to Karara, QLD (12 sites)
Value
$4.1M
Project Duration
2 months